Gwynt y Môr: Notice to Mariners – Pamela P to commence diving operations

On the 12th October 2013 the vessel Pamel P is due to begin diving operations at various turbine locations in the Gwynt y Môr windfarm site until further notice.

A Notice to Mariners about these operations can be downloaded here and is summarised below.

Pamela P is a 12m work boat and will operate a 500m exclusion zone when on site and carrying out operations.  All vessels are requested to pass at slow speed.  Information about Pamela P and a link to her details on MarineTraffic.com are given below:-

Pamela P will monitor VHF Channel 16 at all times.  Vessels may also contact guard vessel Isadale on VHF Channel 16 for further information.

Please contact Jim Andrews, Fishery Liaison Officer by e-mail or phone (+44(0)7908-225865) if you have any queries or concerns about this notice.

This entry was posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm. Bookmark the permalink.