Gwynt y Môr Wind Farm: Project Update

Please find attached a draft notice to mariners about this project, to keep you informed of plans for its development (here).

In a nutshell, the plans are:-

  • At present – Field survey being carried out by Osiris.
  • Mid July 2011 – Trinity House to install buoys which demark the GyM field boundary.
  • August 2011 – Some scour works possibly taking place infield (more likely to be early next year).
  • November 2011 – Construction vessel arrives in Birkenhead.
  • December 2011 – (At earliest) – Will commence offshore monopile installation.

We will keep you updated with further news.  If you have any queries about the project please get in touch with us.