This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 27th August 2012 to harbour masters and sea users. This notice describes recent operations, work planned for the next 7 days, and provides a list of vessels operating on the site with their contact details.
Work carried out over past 7 days
The following work has been carried out in the past week:
- Stanislav Yudin continued foundation installation duties, and installation of ISP West (OSPW arrived on site on 27th August 2012) assisted by support vessels Anglian Monarch and the Smit Angola.
- Penrhos Bay and Malltraeth Bay have been used as a CTV / Stand by vessel when required, running out of Conwy Marina or Deganwy.
- Colwyn Bay and Tremadoc Bay based at Liverpool Marina to be utilised as and when required.
- Choice has been on guard vessel duties (see Notice to Mariners 13 here).
- Cable barge Cable Enterprise and support vessels Fairplay 27, Whalsa Lass andMCS Ailsa continued to lay the export cable from Pensarn Beach towards OSP East (see Notice to Mariners 14 here).
- DP Vessel Sentinel continues with site clearance operations at the windfarm (see notice here).
- Smit Barge 12 has been on standby in Vittoria Dock.
- Viking Barge 5 has been transporting components to site, assisted by tugs Smit Buffalo, Smit Beluga & Union Boxer.
- Viking Barge 3 has been transporting components to site, assisted by tugs Smit Buffalo, Smit Beluga & Union Boxer.
- Toisa Warrior continued with grouting operations, following Stanislav Yudin‘s transition piece installation programme.
- Sarah Jane Too completed noise monitoring operations when piling operations were being conducted.
- Terramare 1 commenced diving operations (see Notice to Mariners 18 here)
Work planned for next 7 days
The work planned for the next 7 days on the site is:
- Stanislav Yudin will continue installation of monopiles and transition pieces, and will install Substation West topside, supported by Smit Angola, Anglian Monarch and Union Boxer.
- Penhros Bay and Malltraeth Bay will continue to be utilised as Crew Transfer / Stand by vessel, running out of Conwy Marina or Deganwy.
- Tremadoc Bay and Colwyn Bay will sail from Liverpool Marina.
- Choice will remain on station as guard vessel.
- Cable barge Cable Enterprise and support vessels Fairplay 27, Whalsa Lass and MCS Ailsa will continue export cable installation from Pensarn Beach towards OSP East.
- DP Vessel Sentinel will commence site clearance operations in the windfarm area (see Notice to Mariners 16 here).
- Viking Barge 5 shall complete mobilisation and will standby for the arrival of installation vessel Stanislav Yudin.
- Toisa Warrior will continue grouting operations as transition pieces are installed at Gwynt y Môr Offshore Windfarm.
- DSV Terramare 1 will commence diving operations on site.
List of vessels at site for next 7 days
The vessels that will be operating on the site over the next 7 days and their contact details are given below. We have linked up the vessel names to MarineTraffic.com so that with just one mouse click you can find out more about their current location and recent activity.
- Penrhos Bay: Crew transfer vessel | Call sign 2DLB8
- Malltraeth Bay: Crew transfer vessel | Call sign 2FGW7
- Tremadoc Bay: Crew transfer vessel | Call sign 2FHG8
- Colwyn Bay: Crew transfer vessel | Call sign 2CYE6
- Choice: Marine Mammal Observation Vessel / Guard Vessel.
- MCS Ailsa: Multicat for export cable barge | Call sign – 5BDK3
- Cable Enterprise: cable barge | Call sign 2FOV9
- Whalsa Lass: multicat for expert cable barge | Call Sign – 2EZQ4
- Fairplay 27: lead tug for export cable barge | Call sign 9HZE9
- Sentinel: DP trawler | Call sign IBXS
- Stanislav Yudin: heavy lift vessel | Call sign 5BYM2
- Anglian Monarch: support vessel for Stanislav Yudin | Call sign MYFR6
- Smit Angola: anchor handling barge | Call sign C6YI5
- Union Boxer: anchor handling vessel | Call sign ORPS
- Toisa Warrior: multi purpose offshore vessel | Call sign C6XY7
- Smit Tiger: tug | Call sign ORPO
- Terramare 1 | Diving support vessel | Call sign ZQWK6
All vessels will monitor VHF Channel 16.
Port Arrivals
The planned port arrivals over the next 7 days are:-
- Cammel Laird Birkenhead/Port of Liverpool.
- Smit Buffalo & Smit Beluga, on a daily basis within Tranmere Wet Basin.
- Viking Barge 3 and Viking Barge 5 supported by Union Boxer and 2 Smit tugs on a continuous basis from Tranmere Wet Basin towards the “Q1” Buoy.
- Marlene, expected 28th August.
- Sea Breeze 2 expected 29th August
- Mostyn.
- No movements expected.
- Liverpool marina
- Tremadoc Bay & Colwyn Bay on a daily basis.
- Conwy / Deganwy
- Penrhos Bay & Malltraeth Bay standing by in port when not utilised.
Please contact Jim Andrews, Fishery Liaison Officer by e-mail or phone (+44(0)7908-225865) if you have any queries or concerns about these activities.