A newsletter detailing progress with the construction of the Gwynt y Môr website has just been published. You can download a copy here, and we’ve summarised the key points below:-
- Offshore
- More than 40 turbine foundations have now been installed by the vessels Stanislav Yudin and Friederich Ernestine.
- One of the export cables from the site is being installed by the vessel Cable Enterprise.
- Onshore
- Six new apprentices have started training as wind turbine technicians at Coleg Llandrillo Menai in Conwy.
- A new wind turbine training centre is being established at Coleg Llandrillo Menai in Conwy with the support of RWE NRL.
- Members of Cefn Meiriadog Community Council visited the new onshore substation at St Asaph.
- Four noise monitoring stations have been established along the North Wales coast.
- A 24-hour noise hotline has been established for the project (phone number 0845 026 0587).
Please contact Jim Andrews, Fishery Liaison Officer by e-mail or phone (+44(0)7908-225865) if you have any queries or concerns about these activities.