Gwynt y Môr Windfarm: Weekly Progress Report, 21st January 2013

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 21st January 2013 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and provides a list of vessels operating on the site with their contact details.

Wind Farm Construction Status

Progress with construction progress is illustrated in a map here, and summarised below:-

  • Monopiles: 80 installed, 80 remaining
  • Transition pieces: 58 installed, 102 remaining
  • Export cables: 1st cable (East) laid, still to be joined.  2nd cable (East) now due to be laid in summer 2013.
  • Array cables: work not commenced

Navigation Hazards

There are presently a number of navigation hazards in and around the windfarm area.  These include:-

  • Unlit objects – there is presently 1 unlit monopile within the windfarm boundary.  Our latest update about these hazards can be accessed here.
  • Exposed monopiles – there are currently 22 exposed monopiles, which may be submerged at certain states of tide.  These are detailed in our previous notice here.

The location of these hazards is shown in a map here.

Work carried out over past 7 days

The following work has been carried out in the past week:

  • Friederich Ernestine continued drilling, piling and transition piece installatin at turbine location F10H.
  • Penrhos Bay, Malltraeth Bay, Penrhyn Bay, Caernarfon Bay, Chinook and Scirocco utilised as Crew Transfer Vessels when required and sailed from Liverpool Marina and Canada Dock 3.
  • Colwyn Bay and Kinmel Bay utilised as Crew Transfer / Stand by vessel as required and based at Liverpool Marina.
  • Isadale continued work as a guard vessel and has been located at the export cable laydown point, south of Gwynt y Môr Offshore Wind Farm.
  • Fleur de Lys has commenced Marine Mammal Observation duties for piling at Gwynt y Môr Offshore Wind Farm.
  • Normand Tonjer continued bung installation and support for Friederich Ernestine.
  • Pulsar carried out survey work of the wet basis at base harbour, Holyhead.
  • Whalsa Lass recovered the FLIDAR buoy from Gwynt y Môr Offshore Wind Farm.
  • Seatruck Pace delivered the first set of wind turbine generator parts to Mostyn.

Work planned for next 7 days

The work planned for the next 7 days on the site is:

  • Friederich Ernestine will continue installation of transition piece at F10H then F13F and then return to Base Harbour for her next batch of components.
  • Tremadoc Bay, Colwyn Bay, Kinmel Bay, Penryn Bay, Penhros Bay, Malltraeth Bay, Caernarfon Bay, Chinook and Scirocco will be utilised as Crew Transfer / Stand by vessels running out of Liverpool Marina and Canada Dock, Liverpool.
  • Normand Tonjer will continue with diving operations.
  • Isadale will continue to guard the export cable south of Gwynt y Môr Offshore Wind Farm.
  • Fleur de Lys will continue with Marine Mammal Observeration duties.
  • Whalsa Lass will reinstall the FLIDAR buoy at Gwynt y Môr Offshore Wind Farm.

List of vessels at site for next 7 days

The vessels that will be operating on the site over the next 7 days and their contact details are given below.  We have linked up the vessel names to MarineTraffic.com so that with just one mouse click you can find out more about their current location and recent activity.

All vessels will monitor VHF Channel 16.

Port Arrivals

The planned port arrivals over the next 7 days are:-

  • Cammel Laird Birkenhead/Port of Liverpool.
    • Coasters Joerg NBenteMarlene and Manual Access Platform (MAPs) delivery vessels will continue to deliver components to Base Harbour at Birkenhead on a regular basis.
    • Construction vessels and support vessels may enter Liverpool at short notice to change crew and collect stores.
  • Mostyn.
    • No movements expected.
  • Liverpool marina / Cammell Lairds wet basin / Canada Dock
    • Tremadoc Bay, Colwyn Bay, Kinmel Bay, Penrhyn Bay, Penrhos Bay, Malltraeth Bay, Caernarfon Bay, Chinook & Scirocco on a daily basis.

Please contact Jim Andrews, Fishery Liaison Officer by e-mail or phone (+44(0)7908-225865) if you have any queries or concerns about these activities.

This entry was posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm. Bookmark the permalink.