Category Archives: Gwynt y Môr Offshore Wind Farm

Gwynt y Môr: Notice to Mariners – Disposal of Unexploded Ordnance

Three unexploded devices were discovered in the Gwynt y Môr Offshore Wind Farm recently.  They will soon be disposed of using controlled explosions.  Further details are given in the Notice to Mariners here which is summarised below. Disposal of UXO … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 17th March 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 17th March 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged | Leave a comment

Gwynt y Môr: Notice to Mariners – Unexploded Ordnance

Three unexploded devices were discovered in the Gwynt y Môr Offshore Wind Farm recently.  This notice provides information about an exclusion zone that has been established around this unexploded ordnance (UXO) and the plans to remove the objects. Removal of … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 10th March 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 10th March 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 4th March 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 3rd March 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr: Notice to Mariners – Site Survey work

A Notice to Mariners about some survey work that is due to be carried out within Gwynt y Môr Offshore Wind Farm has been issued.  The notice is summarised below and can be downloaded here. Seabed Investigations From the 28th February … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 24th February 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 24th February 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 17th February 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 17th February 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 10th February 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 10th February 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 3rd February 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 3rd February 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment