Category Archives: Gwynt y Môr Offshore Wind Farm

Gwynt y Môr Windfarm: Weekly Progress Report, 22nd July 2013

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 22nd July 2013 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Temporary Substation Exclusion Zone, 18th July 2013

On the 18th July 2013, engineers are due to be carrying out electrical commissioning work on the Offshore Substation East within the Gwynt y Môr windfarm area. All vessels are requested to observe a 500m exclusion zone around the OSPE … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 15th July 2013

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th July 2013 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: navigation warning about installation of monitoring buoys

A Floating Light Detection and Ranging (FLIDAR) buoy together with a Wave Rider Buoy (WRB) are due to be installed in the vicinity of Gwynt y Môr windfarm during early-mid July 2013.  A Navigation Warning about the installation of these … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 8th July 2013

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th July 2013 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 1st July 2013

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 1st July 2013 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Sea Worker to start wind turbine installation.

On June 26th 2013 the jack up rig Sea Worker will commence Wind Turbine Generator (WTG) installation works at the Gwynt y Môr Offshore Wind Farm.  The Sea Worker will be towed from the Port of Mostyn to the wind farm on a … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 24th June 2013

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 24th June 2013 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 17th June 2013

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 17th June 2013 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment

Gwynt y Môr Windfarm: Weekly Progress Report, 10th June 2013

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 10th June 2013 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Leave a comment