- Gwynt y Môr Export Cable Survey: Update - Fault Identification and Preparatory Works - July 2024
Mariners are advised that maintenance work is due…
- Gwynt y Môr Export Cable Survey: Update - Anchoring Works - July 2024
Mariners are advised that pre-construction work…
- Gwynt y Môr Offshore Wind Farm: Jack up Vessel Operations - July 2024
Mariners are advised that maintenance operations…
- Awel y Môr Proposed Wind Farm: Newsletter Update
The latest newsletter for the Awel y Môr…
- Gwynt y Môr Export Cable Survey: Update - June 2024
Mariners are reminded that a pre-construction…
- Gwynt y Môr Export Cable Survey: Update - Fault Identification and Preparatory Works - July 2024
Category Archives: Gwynt y Môr Offshore Wind Farm
Gwynt y Môr: Arrival of Accommodation Vessel “Wind Solution”
On June 5th 2013 the accommodation vessel Wind Solution is due to arrive in the vicinity of the Gwynt y Môr Offshore Wind Farm. The vessel will be anchored inshore of the wind farm. Further information is provided in the Notice … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 3rd June 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 3rd June 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 27th May 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 27th May 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Mostyn Harbour – Construction of New Pontoon Facility
Construction of a new pontoon facility will start on 1st June 2013 close to No. 1 berth at Mostyn Harbour. This work is expected to take 2 months to complete. A Notice to Mariners describing this work is available for … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 20th May 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 20th May 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 13th May 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 13th May 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr: Foundation Construction Recommencement
The installation of foundations (monopiles) and transition pieces on the Gwynt y Môr Offshore Wind Farm is due to recommence later this month, in mid May 2013. The heavy lifting vessel Stansilav Yudin will be returning to the site to … Continue reading
Gwynt y Môr Offshore Wind Farm: Proposed Vessel Passage Route
The vessel passage route for access to the Gwynt y Môr Offshore Wind Farm has been proposed. This route will be used by construction vessels passing to and from the Port of Mostyn. The route details can be viewed here. … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 6th May 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 6th May 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 29th April 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 29th April 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading