- Gwynt y Môr Export Cable Survey: Update - Fault Identification and Preparatory Works - July 2024
Mariners are advised that maintenance work is due…
- Gwynt y Môr Export Cable Survey: Update - Anchoring Works - July 2024
Mariners are advised that pre-construction work…
- Gwynt y Môr Offshore Wind Farm: Jack up Vessel Operations - July 2024
Mariners are advised that maintenance operations…
- Awel y Môr Proposed Wind Farm: Newsletter Update
The latest newsletter for the Awel y Môr…
- Gwynt y Môr Export Cable Survey: Update - June 2024
Mariners are reminded that a pre-construction…
- Gwynt y Môr Export Cable Survey: Update - Fault Identification and Preparatory Works - July 2024
Category Archives: Gwynt y Môr Offshore Wind Farm
Gwynt y Môr: Geophysical Survey Work
Some geophysical survey operations are due to be carried out on the export cable route from the Gwynt y Môr Offshore Windfarm. These surveys were due to commence on the 20th April 2013. The works are expected to take 1-2 days … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 22nd April 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 22nd April 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr: Offshore Platform Commissioning
The jack-up vessel JB-114 is due to be assisting with commissioning work on the Offshore Platforms in the Gwynt y Môr Offshore Windfarm, starting on 22nd April 2013. A notice about these operations can be downloaded here and is summarised below. JB-114 … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 15th April 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th April 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr: Scour Protection work
Scour protection work is due to recommence on the Gwynt y Môr Offshore Windfarm on the 12th April 2013. The works are expected to take 21 days (subject to weather) and will be carried out by the vessel Tideway Rollingstone. … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 8th April 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th April 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr: Re-scheduled Survey of Export Cable
Bad weather prevented the scheduled survey of the export cable joints (see our earlier notice about this work here). This work is now due to start on the 30th or 31st March 2013. It is likely that the work will … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 25th March 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 25th March 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Gwynt y Môr: Construction notices – cable and wind turbine installation
The construction programme for the Gwynt y Môr is due to step up from the 1st April, with work to recommence on the export cable from the windfarm site, and construction work due to begin on the installation of wind … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 18th March 2013
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 18th March 2013 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading