Our Latest News
- Rhyl Flats Offshore Wind Farm: Update on Heavy Lift Operations, March-April 2026
Mariners are advised of a change to the…
- North Hoyle Offshore Wind Farm: Heavy Lift Operations, March-April 2026
Mariners are advised that the jack up vessel MPI…
- Rhyl Flats Offshore Wind Farm: Heavy Lift Operations, March-April 2026
[The information below has been superceded by a…
- Gwynt y Môr Offshore Wind Farm: Heavy Lift Operations, March 2026
Mariners are advised that maintenance operations…
- Gwynt y Môr Offshore Wind Farm: Survey Operations, February 2026
Mariners are advised that survey operations are…
- Rhyl Flats Offshore Wind Farm: Update on Heavy Lift Operations, March-April 2026
Category Archives: Gwynt y Môr Offshore Wind Farm
Gwynt y Môr Windfarm: Project Update #4
A newsletter detailing progress with the construction of the Gwynt y Môr website has just been published. You can download a copy here, and we’ve summarised the key points below:- Offshore More than 40 turbine foundations have now been installed … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 29th October 2012
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 29th October 2012 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 22nd October 2012
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 22nd October 2012 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 15th October 2012
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th October 2012 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Gwynt y Môr Windfarm: Navigation Hazard Removed
Mariners and sea users are advised that the vessel Cable Enterprise has now recovered the cable plough that has been in wet store off the North Wales coast. Gwynt y Môr Windfarm Navigation Warning 002 (dated 10th September 2012 and … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 8th October 2012
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th October 2012 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
PRIORITY NOTICE Gwynt y Môr Windfarm 8th October 2012: Additional Navigation hazard
A further Navigation Warning advising of Transition Pieces and monopiles with unlit navigation beacons has been issued for the Gwynt y Môr Offshore Windfarm today, 8th October 2012. The full notice can be downloaded here and is summarised below. There are currently fourteen (14) … Continue reading
PRIORITY NOTICE Gwynt y Môr Windfarm: Navigation hazard 5th October 2012
A Navigation Warning advising of Transition Pieces with unlit navigation beacons has been issued for the Gwynt y Môr Offshore Windfarm today, 5th October 2012. The full notice can be downloaded here and is summarised below. There are eleven (11) potential hazards within … Continue reading
PRIORITY NOTICE Gwynt y Môr Windfarm: Navigation hazard 2nd October 2012
A Navigation Warning advising of Transition Pieces with unlit navigation beacons has been issued for the Gwynt y Môr Offshore Windfarm today, 2nd October 2012. The full notice can be downloaded here and is summarised below. There are three (3) transition pieces within … Continue reading
Gwynt y Môr Windfarm: Weekly Progress Report, 1st October 2012
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 1st October 2012 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading