- Gwynt y Môr Export Cable Survey: Update - Fault Identification and Preparatory Works - July 2024
Mariners are advised that maintenance work is due…
- Gwynt y Môr Export Cable Survey: Update - Anchoring Works - July 2024
Mariners are advised that pre-construction work…
- Gwynt y Môr Offshore Wind Farm: Jack up Vessel Operations - July 2024
Mariners are advised that maintenance operations…
- Awel y Môr Proposed Wind Farm: Newsletter Update
The latest newsletter for the Awel y Môr…
- Gwynt y Môr Export Cable Survey: Update - June 2024
Mariners are reminded that a pre-construction…
- Gwynt y Môr Export Cable Survey: Update - Fault Identification and Preparatory Works - July 2024
Category Archives: Gwynt y Môr Offshore Wind Farm
Gwynt y Môr Offshore Wind Farm: revised schedule for Jack up vessel operations, February 2017
Mariners are advised that the maintenance operations within the Gwynt y Môr Offshore Wind Farm that had been scheduled for January 2017 are now due to be carried out during early February 2017. The revised schedule and the scope of this work is set … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Comments Off on Gwynt y Môr Offshore Wind Farm: revised schedule for Jack up vessel operations, February 2017
Gwynt y Môr Offshore Wind Farm: Jack up vessel operations, January 2017
Mariners are advised that maintenance operations are due to be carried out within the Gwynt y Môr Offshore Wind Farm during January 2017. The scope of this work is set out in Notice to Mariners that can be downloaded here and is summarised below … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, Irish Sea, Liverpool Bay, notice to mariners, windfarm
Comments Off on Gwynt y Môr Offshore Wind Farm: Jack up vessel operations, January 2017
Gwynt y Môr: Survey Operations, May 2016
Mariners are advised that two survey operations are due to be carried out in and around the Gwynt y Môr Offshore windfarm during May 2016. One survey will involve a local fishing vessel carrying out scientific fishing survey work as part of … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged Gwynt y Môr, Liverpool Bay, notice to mariners, windfarm
Comments Off on Gwynt y Môr: Survey Operations, May 2016
Gwynt y Môr: Safety notice for fishermen and anglers
This notice clarifies the situation concerning the safe conduct of fishing and angling activities within the Gwynt y Môr Offshore Wind Farm Site. The notice has been issued promote safe operations and provide advice on certain safety issues. Mariners are advised … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged Gwynt y Môr, Irish Sea, Liverpool Bay, notice to mariners, Rhyl Flats, windfarm
Comments Off on Gwynt y Môr: Safety notice for fishermen and anglers
Gwynt y Môr: Export Cable Maintenance Works, December 2015
Mariners are advised that cable maintenance works are due to be carried out on the export cable from the Gwynt y Môr Offshore windfarm starting on or around the 6th December 2015. A Notice to Mariners has been issued in connection with these … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, undersea cable, windfarm
Comments Off on Gwynt y Môr: Export Cable Maintenance Works, December 2015
Gwynt y Môr Windfarm: Operations Report, 22nd September 2015
This is a summary of the notice of operations for the Gwynt y Môr Offshore Windfarm issued on 20th September 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, windfarm
Comments Off on Gwynt y Môr Windfarm: Operations Report, 22nd September 2015
Gwynt y Môr: Survey work starts and diving operations completed, September 2015
Mariners are advised that survey operations are due to be carried out within the Gwynt y Môr Offshore Wind Farm from the 2nd September 2015 from the vessel Channel Chieftain VII. Diving operations that were being carried out from this vessel have now been … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, diving operations, Gwynt y Môr, marine survey, notice to mariners, windfarm
Comments Off on Gwynt y Môr: Survey work starts and diving operations completed, September 2015
Gwynt y Môr: Drilling Operations, September 2015
Mariners are advised that drilling operations are due to be carried out at the location of one of the turbines in the Gwynt y Môr Offshore Wind Farm between the 5th and 15th September 2015 from the vessel Greatship Manisha. A notice … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, notice to mariners, windfarm
Comments Off on Gwynt y Môr: Drilling Operations, September 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 31st August 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 31st August 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 31st August 2015
Gwynt y Môr Windfarm: Weekly Progress Report, 24th August 2015
This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 24th August 2015 to harbour masters and sea users. This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading
Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm
Tagged construction update, Gwynt y Môr, windfarm
Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 24th August 2015