Category Archives: Western High Voltage DC Link

WHVDC Undersea Cable: Survey Update 20th November 2012

An update on the survey work being carried out for the proposed WHVDC undersea cable was issued this week on 19th November 2012.  The update can be downloaded here.  We have summarised the status of the survey below. 2012 survey … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , | Leave a comment

WHVDC Undersea Cable: Survey Update 8th October 2012

An update on the survey work being carried out for the proposed WHVDC undersea cable has been issued today, 8th October 2012.  A notice to mariners about this work was issued in August and can be downloaded here. Survey update A brief … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment

WHVDC Undersea Cable: Survey Update 14th September 2012

An update on the survey work being carried out for the proposed WHVDC undersea cable has been issued today, 14th September 2012.  A notice to mariners about this work was issued last month and can be downloaded here. Survey update A brief … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment

WHVDC Undersea Cable: Survey Update September 2012

An update on the survey work being carried out for the proposed WHVDC undersea cable has been issued today, 3rd September 2012.  A notice to mariners about this work was issued last month and can be downloaded here. Survey update A brief … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment

WHVDC Undersea Cable: Survey Update

An update on the survey work being carried out for the proposed WHVDC undersea cable has been issued today, 17th August 2012.  A notice to mariners about this work can be downloaded here. Survey update A brief summary of progress is … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment

WHVDC Undersea Cable: Survey Underway

The survey work along the WHVDC cable route has commenced today, 26th July 2012. The initial survey work is being carried out by the vessel Granuaile, starting off the Wirral coast and heading northwards along the proposed cable route to … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment

WHVDC Survey Update: 13th July 2012

The survey work along the WHVDC route that was scheduled to begin in Liverpool Bay on the 16th July has been delayed.  It is now due to commence on the 19th July. In preparation for this survey we have added … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment

WHVDC Link: surveys planned for summer 2012

The offshore survey company UTEC has announced the schedule for survey work along the route of the proposed WHVDC Link this summer.  A notice to mariners about this work can be downloaded here.  A brief summary of the survey work … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment

WHVDC Link: Summer 2012 Newsletter published

An update on progress with the Western High Voltage DC Link can be found in the Summer 2012 WHVDC newsletter which has just been published by the National Grid and Scottish Power. The newsletter describes some of the technical characteristics … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment

Project Update: Western High Voltage DC Link

The National Grid and Scottish Power have just released an update on progress with the Western High Voltage DC Link project and an outline of work planned during 2012 and 2013. We have summarised the update briefly below, and you … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Leave a comment