Western HVDC Link: Update on mattressing and cable laying, 19th June 2015

Mariners are advised that concrete mattresses have now been installed at cable crossings along parts of the Western HVDC Link cable route in the Irish Sea, and work on cable installation is due to resume on or around 23rd June 2015. … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link: Update on mattressing and cable laying, 19th June 2015

Western HVDC Link: Cable laying and mattressing, June 2015

[Update – the work described below has now been completed.  This notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record of the notices presently … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link: Cable laying and mattressing, June 2015

Western HVDC Link: Schedule for Landfall, Ardneil & Southannan Sands

[Update – the work described below has now been completed.  This notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record of the notices presently … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link: Schedule for Landfall, Ardneil & Southannan Sands

Western HVDC Link Update: Geophysical and UXO Investigation

Mariners are advised that survey equipment is due to be used in the Irish Sea (Beaufort Dyke) in late February – March 2015.  A Notice to Mariners has been issued for these operations, which is summarised below and can be … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , | Comments Off on Western HVDC Link Update: Geophysical and UXO Investigation

Western HVDC Link Update: Shallow Water Cable Installation, Liverpool Bay, November 2014

Mariners are advised that the first cable laying campaign for the Western HVDC Link has been successfully completed in Liverpool Bay.  A Notice to Mariners advising of progress, the extent of the cable that has been laid, and the location … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link Update: Shallow Water Cable Installation, Liverpool Bay, November 2014

Western HVDC Link: Revised Schedule for Landfall, Ardneil & Southannan Sands

Mariners are advised that operations for the Western HVDC landfall at Ardneil will commence during the week commencing 10th November 2014.  A Notice to Mariners advising about the timetable for operations can be downloaded here and is summarised below.  The previous Notice … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link: Revised Schedule for Landfall, Ardneil & Southannan Sands

Western HVDC Link Update: Notice to Mariners

A Notice to Mariners has been issued today by the Port of Liverpool advising of some areas of exposed cable in Liverpool Bay.  This cable will from part of the Western HVDC Link undersea electricity cable. The full notice can … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link Update: Notice to Mariners

Western HVDC Link Update: Shallow Water Cable Installation, Liverpool Bay, October 2014

Work on the installation of the Western HVDC Link undersea cable is due to start on the seashore of the Wirral and in the inshore waters of Liverpool Bay in October 2014.  A Notice to Mariners advising of the location and extent … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Comments Off on Western HVDC Link Update: Shallow Water Cable Installation, Liverpool Bay, October 2014

Western HVDC Link Update: Shallow Water Cable Installation, Liverpool Bay, October 2014

Work on the installation of the Western HVDC Link undersea cable is due to start on the 5th October 2014 with expected completion by the end of October 2014.  A Notice to Mariners advising of the location and extent of this work … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link Update: Shallow Water Cable Installation, Liverpool Bay, October 2014

Western HVDC Link: Revised Schedule for Landfall, Ardneil & Southannan Sands

Mariners are advised that the proposed installation schedule for the Western HVDC landfall at Ardneil has been slightly adjusted from our original announcement.  The large plastic pipes that will house the cables as they make landfall are now expected to … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link: Revised Schedule for Landfall, Ardneil & Southannan Sands