Category Archives: AWJ Updates

Western HVDC Link: Cable installation update, November 2015

[Update – the work described below has now been completed.  This notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record of the notices presently … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link: Cable installation update, November 2015

Hunterston-Kintyre Cable: Notice of completion of works and details of cable route

Mariners are advised that work has been completed on the Hunterston-Kintyre submarine cable in the Firth of Clyde between Ardneil Bay and Port a’Mhiadair.  A Notice to Mariners has been issued by Peelports announcing the completion of the works.  This … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , , | Comments Off on Hunterston-Kintyre Cable: Notice of completion of works and details of cable route

Moyle Returns Project: Installation Update, 26th October 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A Notice to Mariners has previously been issued for this work, detailing the route and construction schedule.  A … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , , | Comments Off on Moyle Returns Project: Installation Update, 26th October 2015

Undersea Cable Survey Update: Sound of Scalpay, Sound of Gigha, October 2015

Mariners are advised that submarine power cable surveys are due to be carried out in the Sound of Scalpay and the Sound of Gigha during October 2015.  Notices to mariners about this work have been issued for each of these surveys and … Continue reading

Posted in AWJ Updates, Fishery Liaison, SSE Subsea Cable Surveys | Tagged , , , , , | Comments Off on Undersea Cable Survey Update: Sound of Scalpay, Sound of Gigha, October 2015

Moyle Returns Project: Installation Update, 12th October 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A Notice to Mariners has previously been issued for this work, detailing the route and construction schedule.  A … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , | Comments Off on Moyle Returns Project: Installation Update, 12th October 2015

Hunterston-Kintyre Cable: Inshore survey work, October 2015

This notice provides a brief update on progress with on the Hunterston-Kintyre undersea cable in the Firth of Clyde. The vessel Hermes IV has just completed nearshore trenching work at the Kintyre landfall, and is now due to carry out … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Comments Off on Hunterston-Kintyre Cable: Inshore survey work, October 2015

Undersea Cable Surveys: Sound of Scalpay, Sound of Gigha, October 2015

Mariners are advised that submarine power cable surveys are due to be carried out in the Sound of Scalpay and the Sound of Gigha during October 2015.  Notices to mariners about this work have been issued for each of these surveys and … Continue reading

Posted in AWJ Updates, Fishery Liaison, SSE Subsea Cable Surveys | Tagged , , , , , , | Comments Off on Undersea Cable Surveys: Sound of Scalpay, Sound of Gigha, October 2015

Gwynt y Môr Windfarm: Operations Report, 22nd September 2015

This is a summary of the notice of operations for the Gwynt y Môr Offshore Windfarm issued on 20th September 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , | Comments Off on Gwynt y Môr Windfarm: Operations Report, 22nd September 2015

Undersea Cable Surveys: Orkney, September 2015

Mariners are advised that submarine power cable surveys are being carried out in the Orkneys.  Notices to mariners about this work have been issued for each of these surveys and are listed below. Survey locations Surveys are due to be carried out … Continue reading

Posted in AWJ Updates, Fishery Liaison, SSE Subsea Cable Surveys | Tagged , , , | Comments Off on Undersea Cable Surveys: Orkney, September 2015

Hunterston-Kintyre Cable: Rock placement update, 19th September 2015

This notice provides an update on progress with rock placement work on the Hunterston-Kintyre undersea cable in the Firth of Clyde. Rock placement work started on the 9th September with the vessels Seahorse and Rockpiper working close to the Kintyre and Hunterston … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , , | Comments Off on Hunterston-Kintyre Cable: Rock placement update, 19th September 2015