Gwynt y Môr Windfarm: Weekly Progress Report, 8th June 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th June 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 8th June 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 1st June 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 1st June 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 1st June 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 25th May 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 25th May 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 25th May 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 15th May 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th May 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 15th May 2015

Hunterston-Kintyre Cable: UXO Near Arran

Mariners are advised that a suspected unexploded anti-submarine mine has been found during underwater operations for the Hunsterston-Kintyre cable.  A Notice to Mariners has been issued by Clydeport today, 15th May 2015 advising of the location of this UXO.  The … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , , | Comments Off on Hunterston-Kintyre Cable: UXO Near Arran

Gwynt y Môr: Export Cable Maintenance Works, May 2015

Mariners are advised that cable maintenance works are due to be carried out on the export cable from the Gwynt y Môr Offshore windfarm between the 12th May 2015 and early June.  A Notice to Mariners has been issued by Balfour … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr: Export Cable Maintenance Works, May 2015

Western HVDC Link: Cable laying and mattressing, June 2015

[Update – the work described below has now been completed.  This notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record of the notices presently … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link: Cable laying and mattressing, June 2015

Holyhead Deep Tidal Energy Project: Public Exhibition, 21st May 2015, Holyhead

A public exhibition about the proposed Deep Green Holyhead Deep Tidal Energy Project is being held in Holyhead Town Hall on Thursday 21st May, between 10am and 8pm. Everyone with an interest in the project is invited to attend to … Continue reading

Posted in AWJ Updates, Deep Green Holyhead Deep, Fishery Liaison | Tagged | Comments Off on Holyhead Deep Tidal Energy Project: Public Exhibition, 21st May 2015, Holyhead

Hunterston-Kintyre Cable: Pre-Lay Grapnel Run and Guard Vessels

Mariners are advised that Notices to Mariners have been issued by Clydeport concerning the pre-lay grapnel run and the guard vessels for the Hunsterston-Kintyre cable.  A brief summary of each notice is provided below. Pre Lay Grapnel Run A pre-lay … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , | Comments Off on Hunterston-Kintyre Cable: Pre-Lay Grapnel Run and Guard Vessels

Hunterston-Kintyre Cable: Marine installation update, May 2015

Mariners are advised that construction work on the Hunsterston-Kintyre cable is due to start in early May 2015.  A brief summary of these operations is provided below. Works are due to start with laying of concrete mattresses on May 6th. … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , | Comments Off on Hunterston-Kintyre Cable: Marine installation update, May 2015