Gwynt y Môr Windfarm: Weekly Progress Report, 15th March 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th March 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 15th March 2015

Notice to Mariners: Survey of Moyle Interconnector Cable Route

Mariners are advised that marine survey works are due to commence along the Moyle Interconnector cable route on 23rd March 2015 as part of preparations for repair work on the cable route later this year. A notice to mariners describing this work … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , | Comments Off on Notice to Mariners: Survey of Moyle Interconnector Cable Route

Hunterston-Kintyre Cable: Update on Marine Works

Mariners are advised that over the next few days marine survey works are due to continue along the Hunsterston-Kintyre cable route, and that work will be completed on the installation of the HDD conduits in Ardneil Bay, near Hunterston.  A … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , | Comments Off on Hunterston-Kintyre Cable: Update on Marine Works

Gwynt y Môr Windfarm: Weekly Progress Report, 8th March 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 8th March 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 8th March 2015

Hunterston – Kintyre Undersea Cable: Underwater Survey

A Notice to Mariners has been issued advising that survey work is due to start along the route of the Hunterston-Kintyre undersea cable on Monday the 9th March 2015 until or and about Friday 3rd April 2015. The notice can be downloaded … Continue reading

Posted in Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , , | Comments Off on Hunterston – Kintyre Undersea Cable: Underwater Survey

Hunterston – Kintyre Undersea Cable: HDD Landfall, Ardneil Bay, March 2015

Mariners are advised that on the 10th March 2015, a long plastic pipe (500m long and 560mm in diameter) is due to be towed from Hunterston to Ardneil Bay.  This pipe will then be pulled ashore through a hole that has been bored … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , | Comments Off on Hunterston – Kintyre Undersea Cable: HDD Landfall, Ardneil Bay, March 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 1st March 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 1st March 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 1st March 2015

Gwynt y Môr Windfarm: Weekly Progress Report, 22nd February 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 22nd February 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 22nd February 2015

Western HVDC Link Update: Geophysical and UXO Investigation

Mariners are advised that survey equipment is due to be used in the Irish Sea (Beaufort Dyke) in late February – March 2015.  A Notice to Mariners has been issued for these operations, which is summarised below and can be … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , | Comments Off on Western HVDC Link Update: Geophysical and UXO Investigation

Gwynt y Môr Windfarm: Weekly Progress Report, 15th February 2015

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 15th February 2015 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 15th February 2015