Gwynt y Môr Windfarm: Weekly Progress Report, 18th August 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 18th August 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 18th August 2014

Gwynt y Môr Windfarm: Weekly Progress Report, 11th August 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 11th August 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, and … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 11th August 2014

Gwynt y Môr Windfarm: Weekly Progress Report, 4th August 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 4th August 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 4th August 2014

Gwynt y Môr Windfarm: Weekly Progress Report, 28th July 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 28th July 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 28th July 2014

Gwynt y Môr Windfarm: Weekly Progress Report, 21st July 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 21st July 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 21st July 2014

Western HVDC Link: Revised Schedule for Landfall, Ardneil & Southannan Sands

Mariners are advised that the proposed installation schedule for the Western HVDC landfall at Ardneil has been slightly adjusted from our original announcement.  The large plastic pipes that will house the cables as they make landfall are now expected to … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link: Revised Schedule for Landfall, Ardneil & Southannan Sands

Gwynt y Môr Windfarm: Weekly Progress Report, 14th July 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 14th July 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 14th July 2014

Gwynt y Môr Windfarm: Weekly Progress Report, 7th July 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 7th July 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 7th July 2014

Gwynt y Môr Windfarm: Weekly Progress Report, 30th June 2014

This is a summary of the weekly notice of operations for the Gwynt y Môr Offshore Windfarm issued on 30th June 2014 to harbour masters and sea users.  This notice describes progress with construction, recent operations, work planned for the next 7 days, … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , | Comments Off on Gwynt y Môr Windfarm: Weekly Progress Report, 30th June 2014

Western HVDC Link: Geophysical and UXO Survey

Mariners are advised that in August 2014 a geophysical and UXO survey will be carried out at Beaufort’s Dyke in the Irish Sea.  A Notice to Mariners about these operations can be downloaded here and is summarised below. Survey Task The survey … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , , | Comments Off on Western HVDC Link: Geophysical and UXO Survey