Tag Archives: undersea cable

Gwynt y Môr: Export Cable Maintenance Works, December 2015

Mariners are advised that cable maintenance works are due to be carried out on the export cable from the Gwynt y Môr Offshore windfarm starting on or around the 6th December 2015.  A Notice to Mariners has been issued in connection with these … Continue reading

Posted in AWJ Updates, Fishery Liaison, Gwynt y Môr Offshore Wind Farm | Tagged , , , , | Comments Off on Gwynt y Môr: Export Cable Maintenance Works, December 2015

Western HVDC Link: Cable installation update, November 2015

[Update – the work described below has now been completed.  This notice remains as part of the historical record of notices issued for this project.  Please refer to the most recent notice for an up-to-date record of the notices presently … Continue reading

Posted in AWJ Updates, Fishery Liaison, Western High Voltage DC Link, Western Link Undersea Cable | Tagged , , , | Comments Off on Western HVDC Link: Cable installation update, November 2015

Hunterston-Kintyre Cable: Notice of completion of works and details of cable route

Mariners are advised that work has been completed on the Hunterston-Kintyre submarine cable in the Firth of Clyde between Ardneil Bay and Port a’Mhiadair.  A Notice to Mariners has been issued by Peelports announcing the completion of the works.  This … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , , | Comments Off on Hunterston-Kintyre Cable: Notice of completion of works and details of cable route

Moyle Returns Project: Installation Update, 26th October 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A Notice to Mariners has previously been issued for this work, detailing the route and construction schedule.  A … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , , | Comments Off on Moyle Returns Project: Installation Update, 26th October 2015

Undersea Cable Survey Update: Sound of Scalpay, Sound of Gigha, October 2015

Mariners are advised that submarine power cable surveys are due to be carried out in the Sound of Scalpay and the Sound of Gigha during October 2015.  Notices to mariners about this work have been issued for each of these surveys and … Continue reading

Posted in AWJ Updates, Fishery Liaison, SSE Subsea Cable Surveys | Tagged , , , , , | Comments Off on Undersea Cable Survey Update: Sound of Scalpay, Sound of Gigha, October 2015

Moyle Returns Project: Installation Update, 12th October 2015

This is an update on progress with the installation of the Moyle Returns Cables in the North Channel of the Irish Sea.  A Notice to Mariners has previously been issued for this work, detailing the route and construction schedule.  A … Continue reading

Posted in AWJ Updates, Fishery Liaison, Moyle Interconnector Cable | Tagged , , , , , | Comments Off on Moyle Returns Project: Installation Update, 12th October 2015

Undersea Cable Surveys: Sound of Scalpay, Sound of Gigha, October 2015

Mariners are advised that submarine power cable surveys are due to be carried out in the Sound of Scalpay and the Sound of Gigha during October 2015.  Notices to mariners about this work have been issued for each of these surveys and … Continue reading

Posted in AWJ Updates, Fishery Liaison, SSE Subsea Cable Surveys | Tagged , , , , , , | Comments Off on Undersea Cable Surveys: Sound of Scalpay, Sound of Gigha, October 2015

Undersea Cable Surveys: Orkney, September 2015

Mariners are advised that submarine power cable surveys are being carried out in the Orkneys.  Notices to mariners about this work have been issued for each of these surveys and are listed below. Survey locations Surveys are due to be carried out … Continue reading

Posted in AWJ Updates, Fishery Liaison, SSE Subsea Cable Surveys | Tagged , , , | Comments Off on Undersea Cable Surveys: Orkney, September 2015

Hunterston-Kintyre Cable: Rock placement update, 19th September 2015

This notice provides an update on progress with rock placement work on the Hunterston-Kintyre undersea cable in the Firth of Clyde. Rock placement work started on the 9th September with the vessels Seahorse and Rockpiper working close to the Kintyre and Hunterston … Continue reading

Posted in AWJ Updates, Fishery Liaison, Hunterston Kintyre Interconnector Cable | Tagged , , , , | Comments Off on Hunterston-Kintyre Cable: Rock placement update, 19th September 2015

Moyle Returns Project: Update – nearshore rock placement, Scottish landfall

This notice provides a further update on progress with activities for the rock protection of the nearshore sections of the Moyle Interconnector cables.   This work started recently, and progress is summarised briefly below. Nearshore Rock Placement, Scottish Landfall On the … Continue reading

Posted in Fishery Liaison, Moyle Interconnector Cable | Tagged , , , | Comments Off on Moyle Returns Project: Update – nearshore rock placement, Scottish landfall